Agree the test protocol before manufacture
Define acceptable feed characteristics, kg DS/h and flow, schedule, conditioning and available utilities. State which performance criteria must be met simultaneously: throughput, cake solids, capture and consumption. The quotation should identify the permitted sludge variation and responsibility for feed pumping, polymer, cake handling and return liquors.
Agree stabilisation and measurement periods, repeat runs, sampling and laboratory methods. Specify how deviations will be resolved and when repeat testing is appropriate. Avoid purchasing one cake-solids figure without stating the loading, polymer dose and filtrate requirements under which it will be verified. The operating point matters as much as the headline result.
Use FAT to check equipment and functions
Factory acceptance testing can cover equipment identification, critical dimensions, documentation, contract-specified materials and access. Review the signal list and control sequences within the agreed test scope. Where instruments are simulated, distinguish clearly between simulated conditions and functions physically demonstrated on the assembled package.
Running without sludge does not reproduce biological sludge, DAF float or digestate behaviour. The FAT report should record observations and installation-dependent outstanding items without presenting a functional check as evidence of dewatering performance. Reserve site-dependent checks for commissioning and identify any conditions necessary before those checks can proceed.
Measure the operating point during SAT
For site acceptance, sample feed, cake and filtrate during stable periods of the same run. Record mass or flow, concentration, active polymer, water and electricity within the agreed boundary. Verify instruments and account for washing, dilution and streams that do not pass the principal measurement point. Sampling timing should reflect material travel through the line.
Define the capture basis. Total and suspended solids are not interchangeable where dissolved matter is significant. Distinguish reagent-derived solids and explain the mass-balance closure. Drier cake achieved at lower throughput or a substantially greater polymer dose does not establish compliance with the requested operating point. Report all simultaneous results together.
Accept a usable and documented installation
Include starting and stopping, auxiliary availability, cake transport and communication with the treatment plant. Safety checks should follow the competent party’s approved protocol. Complete handover with manuals, operator training, final settings, maintenance instructions and spare-parts information. Preserve results, conditions and deviations in the acceptance report so it becomes a repeatable operating reference and evidence for resolving later technical disputes.
Common questions
Does FAT replace a pilot trial?
Not necessarily. A pilot reduces uncertainty about the sludge before purchase; FAT checks the supplied equipment and agreed functions. The objectives and conditions differ.
Can acceptance rely on a sample supplied months earlier?
That sample can inform preliminary testing. Acceptance should use the sludge and operating range defined in the contract, with justified representativeness and sample handling.