DAF flotation

Industrial DAF price: what the quotation should include

Compare DAF quotations by duty, loading, conditioning, saturation and float handling. Establish the complete supply scope before comparing prices.

Published Updated Prepared by Neptuno Water Technology

Give each supplier the same design basis

Provide average and peak flow, operating hours, suspended solids, grease, pH, temperature and total and filtered COD. Identify cleaning discharges and production changes. A 20 m³/h flow with a low solids concentration does not define the same duty as that flow carrying a much higher solids load.

Investment does not necessarily grow in direct proportion to flow. Effective separation area, air contact, extraction arrangements and materials must suit the stream. Ask which conditions support each stated capacity and how the system handles a peak as well as normal production.

Compare five supply blocks

Separate reception and pumping; pH adjustment and conditioning; flotation with its recycle and saturation circuit; float extraction and handling; and instrumentation and control. Mark every component as included, optional or supplied by the customer. This makes omissions visible before the total prices are compared.

Check reagent preparation and dosing, compressed air, internal pipework, electrical panel, commissioning and external connections. Record transport, unloading, installation and tests separately. These are items to agree for the project rather than assumptions about what every equipment supply must include.

Use your operating data to assess running cost

Calculate commercial reagent consumption per treated cubic metre and measure electricity across the relevant equipment boundary. Add service water, maintenance, operator time and sludge disposal. The scraper motor rating alone does not represent energy consumed by pumps, saturation and auxiliaries.

Illustrative arithmetic: a genuine operating-cost difference of €0.10/m³ at 100,000 m³/year amounts to €10,000/year. This is neither a predicted saving nor a market price. It helps identify which operating measurements are worth obtaining before choosing between capital proposals.

Follow the float to its final destination

Define float storage, transfer pumping and dewatering hours. Processes delivering similar clarification can generate sludge with different volumes, mineral contents and polymer responses. Compare costs through to the point where residue leaves the facility rather than stopping at the flotation tank.

If a screw press is included, size its feed duty using dry-solids mass and effective operating hours. Confirm the destination or treatment of filtrate. Crediting DAF with all COD removal or ignoring return streams can conceal an integration cost or an unmet downstream requirement.

Link the quotation to a representative trial

Agree which sample represents production, what will be measured and the test duration. Define acceptance against flow, outlet solids and grease, stability and consumptions. Dissolved COD, salts and substances remaining in solution require a separate downstream assessment.

Neptuno can develop a supply scope against this common basis. An early budget should state unresolved inputs and its level of definition. A firm proposal requires the variables affecting equipment, process performance and integration cost to be resolved.

Sources and documentation

Your project with Neptuno

Get a proposal for your project.

Tell us what you need to solve in your process. Start with the information you have.

We will review the application and explain the solution we can supply or the information needed to assess it.

Contactcomercial@neptunoes.comEmail water analyses, photographs and drawings to our sales address.
TECHNICAL CONTACT

Tell us about your project.

Tell us what you need and we’ll propose a solution.

Add process details (optional)

NEPTUNO WATER TECHNOLOGY SL will use your details to handle the enquiry. Your rights and further information are in the privacy policy.