High-solids ultrafiltration

When and how to pilot crossflow UF on high-solids wastewater

UF trial protocol for net flux, concentration, cleaning and both outlet destinations before sizing.

Published Updated

Set acceptance criteria before starting

Define feed flow and composition, and permeate and concentrate quality targets. Describe expected variability across shifts, batches, seasons, start-ups and plant washes. Set thresholds for net production, cleaning recovery, outlet quality and availability that would make the project viable.

Document module, area, instruments, sampling method and feed conditions. A uniform laboratory sample may miss fibres or production discharges.

  • Log feed, permeate, purge and recirculation flow.
  • Measure relevant TSS/TS, total/soluble COD, viscosity, oil, pH and temperature.
  • Time-stamp pressures, TMP, electricity and consumables.

Test the whole cycle and final concentration

Start with a stable baseline and move in stages to the target concentration factor. Measure flux and TMP through each cycle, after backwash and after CIP. Flux decline and subsequent recovery separate reversible deposits from persistent loss.

Close water and solids balances to find settling or unrepresentative samples. As viscosity rises, check that pumps, mixing and pipework retain enough margin.

OutcomeAcceptance question
Net fluxDoes it include washing and availability?
ConcentrationCan it still be pumped?
PermeateDoes it meet the next use or treatment step?
CIPDoes it restore output without material damage?

Scale with uncertainty

A proposal should state the measured range and design allowance, plus conditions the trial did not represent. A short pilot does not prove seasonality or membrane life. If chemistry, pretreatment or outlet destinations change, revisit the design.

State who will review the pilot record and what decisions follow each failure. If permeate quality fails, first identify the passing component; if flux fails, distinguish reversible deposits from permanent loss. An acceptance report should retain raw data and the assumptions used for scale-up.

Common questions

Is a clean-water trial enough?

It can provide a hydraulic or integrity baseline; it does not reproduce fouling, concentration or net production on real wastewater.

Sources and documentation

Your next step

Request a technical proposal.

Tell us the flow rate, water quality and treatment objective.

We will review equipment selection, integration and the data needed to size your project.

Send project detailscomercial@neptunoes.comThe form opens here. You can also email us directly.
TECHNICAL CONTACT

Tell us about your project.

Send us the basics and we will follow up to shape the proposal.

We will use your details only to reply to this enquiry.